Siemens Energy delivers technology for
seventh offshore wind farm connection in the North Sea
Low-loss transmission of wind
energy for 1.1 million households
Further contribution toward
decarbonizing energy supplies
Siemens Energy is supplying the
high-voltage direct-current (HVDC) power transmission technology for a further
offshore connection in the German North Sea. A corresponding contract was just
signed by the German-Dutch network operator TenneT and the BorWin5 Offshore
Consortium, consisting of Siemens Energy and Dragados Offshore. In 2025, the
platform BorWin epsilon, which is part of the BorWin5 project, will begin the
low-loss transmission of electricity produced by the EnBW He Dreiht wind farm
off the island of Borkum to the Garrel/Ost converter station around 230
kilometers distant. The transmission capacity of 900 megawatts is calculated to
serve over 1.1 million households with electricity. The project is a further
contribution toward decarbonizing Germany’s energy supply. BorWin5 marks the
seventh HVDC offshore grid connection project undertaken by Siemens Energy in
Germany with TenneT.
Low-loss transmission of wind
energy for 1.1 million households
Further contribution toward
decarbonizing energy supplies
Siemens Energy is supplying the
high-voltage direct-current (HVDC) power transmission technology for a further
offshore connection in the German North Sea. A corresponding contract was just
signed by the German-Dutch network operator TenneT and the BorWin5 Offshore
Consortium, consisting of Siemens Energy and Dragados Offshore. In 2025, the
platform BorWin epsilon, which is part of the BorWin5 project, will begin the
low-loss transmission of electricity produced by the EnBW He Dreiht wind farm
off the island of Borkum to the Garrel/Ost converter station around 230
kilometers distant. The transmission capacity of 900 megawatts is calculated to
serve over 1.1 million households with electricity. The project is a further
contribution toward decarbonizing Germany’s energy supply. BorWin5 marks the
seventh HVDC offshore grid connection project undertaken by Siemens Energy in
Germany with TenneT.
“We are especially pleased that we can
again join with TenneT to make an important contribution to the decarbonization
of Germany’s energy supply. The seventh order in the German North Sea
underscores the great confidence in our HVDC technology,” emphasizes Beatrix
Natter, Executive Vice President of the Transmission Division at Siemens
Energy. “When DolWin6 and BorWin5 begin operation, we’ll have installed a total
transmission capacity for 5.6 gigawatts of wind power in the German North Sea. This
could supply around seven million German households with green electricity.”
The scope of supply for Siemens Energy and its Spanish partner Dragados Offshore S.A. includes the turnkey construction and installation of the offshore platform in the North Sea and the converter station on land. The offshore converter station will convert the three-phase alternating current produced by the wind turbines into direct current with a voltage of ±320 kilovolts(kV) for low-loss transmission to land. The shoreside converter station in Garrel/Ost will then convert the electricity back into three-phase alternating current for feeding into Germany’s power grid. Siemens Energy will supply the HVDC technology required for the project and build the shoreside station, while Dragados will be responsible for the design, procurement, construction and installation of the offshore converter platform.
Together with
its partners, Siemens Energy has already built and installed five offshore HVDC
connections in the German North Sea for TenneT. The DolWin6 and BorWin5 projects
are currently being implemented.
Siemens Gas and Power GmbH & Co. KG is the global energy business of the Siemens group, which has been working with its customers on solutions for the evolving demands of industry and society for more than 150 years. With planned stock listing, Siemens’ energy business will operate independently as Siemens Energy in the future. It will offer broad expertise across the entire energy value chain, along with a comprehensive portfolio for utilities, independent power producers, transmission system operators, the oil and gas industry, and other energy-intensive industries. With its products, solutions, systems, and services, Siemens Energy will address the extraction, processing, and transport of oil and gas as well as power and heat generation in central and distributed thermal power plants, and power transmission and technologies for the energy transformation, including storage and sector-coupling solutions. The majority stake in Siemens Gamesa Renewable Energy will round out its future-oriented portfolio. With its commitment to leading the way in decarbonization of the global energy system, Siemens Energy will be a partner of choice for companies, governments, and customers on their path to a more sustainable future. With around 90,000 employees worldwide, Siemens Energy will help shape the energy systems of today and tomorrow.